Arbitration Connected To Indonesian Lng High-Pressure Pipeline Strikes

1. Technical and Contractual Background

In Indonesian LNG projects, high-pressure pipelines transport natural gas between:

Upstream facilities and LNG liquefaction plants

Storage, regasification, and export terminals

Offshore platforms and onshore processing units

A pipeline strike—typically caused by excavation, piling, dredging, or marine construction—can result in:

Immediate gas release and safety shutdowns

Fire or explosion risk

Extended plant outages and LNG cargo delays

Regulatory intervention and reputational damage

Such disputes commonly arise under:

EPC and Design-Build contracts

Pipeline installation and protection agreements

Third-party construction or dredging contracts

O&M agreements and right-of-way arrangements

Arbitration focuses on duty of care, pipeline protection measures, disclosure of pipeline data, and allocation of third-party risk.

2. Typical Arbitration Issues in Pipeline Strike Disputes

2.1 Pipeline Location and Disclosure

Whether accurate as-built drawings and GIS data were provided to contractors.

2.2 Duty to Protect and Mark Pipelines

Adequacy of burial depth, concrete coating, warning tapes, and exclusion zones.

2.3 Contractor Negligence

Failure to follow permit-to-work, excavation clearance, or marine exclusion procedures.

2.4 Force Majeure and Third-Party Acts

Whether a pipeline strike constitutes force majeure or a foreseeable construction risk.

2.5 Consequential Loss and Shutdown Damages

Claims for LNG cargo delay, lost production, and contractual penalties.

2.6 Insurance and Indemnity

Interpretation of CAR, third-party liability, and business interruption coverage.

3. Illustrative Case Laws (Arbitral Case References)

Case 1: Indonesian LNG Operator vs EPC Contractor

Issue: High-pressure pipeline struck during foundation piling works inside LNG plant boundary.
Tribunal Finding: EPC contractor failed to comply with approved excavation and verification procedures.
Outcome: Contractor liable for repair costs, shutdown losses, and safety remediation expenses.

Case 2: LNG Project Company vs Marine Dredging Contractor

Issue: Offshore pipeline damaged during dredging for LNG jetty approach channel.
Tribunal Finding: Contractor ignored pipeline exclusion zone shown in marine drawings.
Outcome: Full liability imposed on dredging contractor for pipeline repair and LNG export delay damages.

Case 3: LNG Operator vs Engineering Consultant

Issue: Consultant provided inaccurate pipeline route drawings used during construction.
Tribunal Finding: Consultant negligent in failing to update as-built alignment data.
Outcome: Consultant held partially liable; damages apportioned with construction contractor.

Case 4: LNG Joint Venture vs International EPC Consortium

Issue: Consortium claimed pipeline strike was force majeure due to undocumented legacy pipeline.
Tribunal Finding: Risk of undocumented pipelines was foreseeable and required pre-construction surveys.
Outcome: Force majeure rejected; EPC consortium liable for resulting losses.

Case 5: LNG Operator vs Third-Party Utility Contractor

Issue: Third-party utility contractor struck gas pipeline during roadworks near LNG facility.
Tribunal Finding: Contractor failed to obtain clearance and conduct trial excavation.
Outcome: Contractor ordered to indemnify LNG operator for repair costs and lost production.

Case 6: LNG Operator vs Insurer

Issue: Insurer denied coverage, asserting damage resulted from contractor negligence.
Tribunal Finding: Policy covered accidental physical damage regardless of fault allocation.
Outcome: Insurance payout granted for repair and business interruption losses, with insurer subrogation rights preserved.

4. Key Legal and Technical Principles Applied by Tribunals

Foreseeability of Pipeline Strike Risk

Excavation and dredging risks are rarely treated as extraordinary.

Strict Compliance with Permit-to-Work Systems

Failure to follow clearance procedures weighs heavily against contractors.

Shared Liability Where Information Is Defective

Inaccurate drawings often result in apportioned damages.

High Standard of Care for High-Pressure Gas Lines

Tribunals impose enhanced duty due to catastrophic risk potential.

Force Majeure Narrowly Interpreted

Third-party acts are not force majeure if controllable through procedures.

Insurance as Risk Allocation Tool

Coverage often applies even where liability is disputed.

5. Practical Lessons for LNG Projects in Indonesia

Maintain accurate, updated as-built pipeline data.

Enforce strict excavation and marine exclusion protocols.

Clearly allocate third-party pipeline strike risk in contracts.

Require pre-construction surveys and trial digs.

Align insurance coverage with pipeline exposure and shutdown risk.

LEAVE A COMMENT