Swiss Tribunals’ Evaluation Of Concurrent Delay Claims

I. Concept of Concurrent Delay in Swiss Arbitration

1. What Is Concurrent Delay

Concurrent delay arises where:

Two or more delay events overlap in time, and

At least one delay is attributable to the employer/owner, and

At least one delay is attributable to the contractor/designer.

Typical contexts include:

Infrastructure and EPC projects

Design-and-build contracts

Large-scale industrial facilities

PPP and concession projects

Swiss law does not contain an explicit statutory doctrine of concurrent delay. Instead, Swiss tribunals approach concurrency through:

Causation

Burden of proof

Contractual risk allocation

Equitable assessment of damages

II. Legal Framework Applied by Swiss Tribunals

A. Procedural Law

Art. 182 PILA – broad procedural discretion

Art. 190(2)(d) PILA – review limited to due process

B. Substantive Law (often Swiss law)

Art. 97 CO – liability for breach

Art. 42 CO – proof of damage

Art. 44 CO – reduction of damages due to contributory fault

Art. 99 CO – causation and fault principles

Art. 2 CC – good faith

These provisions allow tribunals to address concurrency without importing rigid common-law rules.

III. Core Principles in Swiss Evaluation of Concurrent Delay

Swiss tribunals consistently apply the following principles:

Primacy of causation over labels

No automatic time-bar due to concurrency

Separation of time entitlement and cost entitlement

Apportionment where causation cannot be disentangled

Equitable assessment where proof is inherently difficult

Heavy reliance on expert delay analysis

IV. Swiss Federal Supreme Court Case Law

1. SFSC Decision BGE 132 III 122

Causation as the Central Test

Principle:
Liability for delay depends on whether the breach was a natural and adequate cause of the delay.

Holding:

Where multiple causes exist, liability may still arise

The tribunal must examine causal contribution, not exclusivity

Relevance:
Foundation for rejecting “all-or-nothing” approaches to concurrency.

2. SFSC Decision BGE 136 III 395

Apportionment of Responsibility

Principle:
Where both parties contribute to the damage, damages may be reduced proportionally.

Holding:

Art. 44 CO permits apportionment

Mathematical precision is not required

Application:
Directly supports proportional treatment of concurrent delays.

3. SFSC Decision 4A_150/2012

Duty to Address Delay Analysis

Principle:
Tribunals must engage with the core delay arguments, even if they reject them.

Holding:

Failure to address decisive concurrency submissions may violate the right to be heard

However, tribunals are not obliged to adopt a specific delay methodology

Importance:
Confirms tribunal freedom in choosing delay-analysis techniques.

4. SFSC Decision 4A_277/2012

Flexibility in Evidentiary Management

Principle:
Tribunals may adapt the evidentiary record where concurrency issues evolve.

Holding:

Admission of supplemental delay-expert reports upheld

Concurrency analysis often matures late in proceedings

Significance:
Critical for complex infrastructure arbitrations.

5. SFSC Decision BGE 138 III 374

Good Faith and Delay Attribution

Principle:
A party contributing to delay may not recover damages as if it were blameless.

Holding:

Good faith requires tribunals to consider mutual causation

Prevents strategic delay claims ignoring own responsibility

Relevance:
Used to reject full recovery in concurrent delay scenarios.

6. SFSC Decision 4A_162/2015

Use of Tribunal-Appointed Experts

Principle:
Tribunal-appointed experts are appropriate where concurrency is technically complex.

Holding:

No breach of equality of arms

Parties must be allowed to comment and question the expert

Impact:
Encourages neutral delay analysis in concurrency disputes.

7. SFSC Decision 4A_65/2018

Global and Equitable Assessment of Delay Damages

Principle:
Where precise allocation is impossible, tribunals may assess damages on an equitable basis.

Holding:

Lump-sum or percentage-based reductions upheld

Particularly suitable for overlapping delay causes

Importance:
Frequently cited in Swiss-seated EPC arbitrations.

V. Swiss Tribunal Practice on Time vs. Money

Swiss tribunals typically separate:

A. Extension of Time (EOT)

Often granted even where delays are concurrent

Focus on whether employer-caused delay prevented timely completion

B. Delay Damages / Prolongation Costs

Reduced or denied where contractor contributed to delay

Apportioned using Art. 44 CO principles

This approach avoids the rigidity of the common-law “no damages for concurrent delay” rule.

VI. Delay Analysis Methodologies

Swiss tribunals:

Do not mandate a specific method (CPM, windows, as-planned vs. as-built)

Focus on persuasiveness and transparency

Accept hybrid and pragmatic analyses

Prefer expert evidence over doctrinal purity

Courts will not review:

Choice of methodology

Technical correctness of scheduling analysis

VII. Standard of Judicial Review

Under Art. 190 PILA, the SFSC:

Will not reassess causation or delay apportionment

Will not replace the tribunal’s technical judgment

Intervenes only for:

Failure to address decisive arguments

Arbitrary exclusion of evidence

Fundamental procedural unfairness

This creates high predictability for concurrent delay determinations.

VIII. Key Takeaways

Swiss law rejects rigid concurrency doctrines.

Causation, not exclusivity, governs liability.

Apportionment is expressly permitted under Art. 44 CO.

Time and cost consequences are treated separately.

Equitable and global assessments are accepted.

Swiss courts show strong deference to arbitral findings.

IX. Summary Table

IssueSwiss Position
Arbitrability of delay claimsFully arbitrable
Concurrent delay doctrineFlexible, causation-based
ApportionmentPermitted
Extension of timeOften granted
Delay damagesReduced or denied if concurrent
Expert relianceStrong
Annulment riskVery low

LEAVE A COMMENT