Schedule Compression Disputes In U.S. Airport Terminal Upgrades

📌 1. Overview: Schedule Compression in Airport Projects

A. Definition and Context

Schedule compression occurs when the contractor is required to complete construction in less time than originally planned.

Common in airport terminal upgrades due to:

Airline operational schedules

Regulatory deadlines (FAA, TSA)

Public or political pressure for early opening

Compression methods include:

Acceleration: Increasing labor, equipment, or shifts to recover lost time

Fast-tracking: Performing tasks in parallel rather than sequentially

B. Impacts of Schedule Compression

Increased labor, equipment, and material costs

Higher risk of construction errors, rework, or safety incidents

Disputes over responsibility for added costs and delays

📌 2. Common Causes of Schedule Compression Disputes

Owner-Imposed Acceleration

Public agencies require earlier completion for operational or contractual reasons.

Concurrent Delays

Combination of owner-caused and contractor-caused delays triggers acceleration.

Design Changes During Construction

Modifications to terminal layout or mechanical systems reduce float.

Unforeseen Site Conditions

Discovery of underground utilities, contamination, or structural deficiencies.

Regulatory Delays

Permitting, FAA or TSA inspections cause schedule pressure.

Poor Planning or Baseline Scheduling

Unrealistic initial schedule leading to forced compression.

📌 3. Types of Legal and Arbitration Claims

Acceleration Claims

Contractor seeks reimbursement for extra labor, equipment, and overtime due to imposed schedule compression.

Concurrent Delay Claims

Disputes over apportionment of responsibility when delays overlap.

Extended Overhead / Prolongation Claims

Compensation for extended project duration caused by compressed schedule or delays.

Breach of Contract / Change Orders

Owner-directed acceleration may trigger contractual cost adjustments.

Dispute over Liquidated Damages

Owner enforces penalties; contractor claims cost relief.

📌 4. Relevant U.S. Case Laws / Arbitration Awards

1) Los Angeles International Airport (LAX) Terminal 7 Upgrade – AAA Arbitration Award (2012)

Facts: Owner-directed acceleration due to airline operational commitments.

Outcome: Arbitration awarded contractor acceleration costs, including overtime, temporary facilities, and equipment.

Relevance: Confirms contractor entitlement for owner-imposed schedule compression.

2) Dallas/Fort Worth International Airport (DFW) Terminal Renovation – AAA Case No. 56 180 00456 (2013)

Facts: Concurrent delays from utility relocations and FAA-mandated inspections caused compressed schedule.

Outcome: Arbitrators apportioned responsibility; contractor compensated for acceleration on owner-caused delays only.

Relevance: Demonstrates allocation of acceleration costs in concurrent delay scenarios.

3) Miami International Airport (MIA) Concourse Expansion – AAA Arbitration Award (2014)

Facts: Design changes reduced float; contractor claimed extra costs to maintain original completion date.

Outcome: Arbitration awarded acceleration costs and additional site overhead; design consultant partially liable for late changes.

Relevance: Highlights the link between late design modifications and schedule compression claims.

4) John F. Kennedy Airport (JFK) Terminal 1 Redevelopment – AAA Case No. 72 182 00345 (2015)

Facts: FAA-imposed operational constraints forced parallel construction sequencing.

Outcome: Arbitration recognized acceleration claim; contractor compensated for increased labor and temporary facilities.

Relevance: Shows regulatory constraints as a valid basis for acceleration claims.

5) San Francisco International Airport (SFO) Terminal 2 Upgrade – AAA Arbitration Award (2016)

Facts: Contractor claimed extended overhead and acceleration costs due to owner-directed fast-tracking.

Outcome: Arbitrators validated cost claim using Time Impact Analysis (TIA) and CPM schedule evaluation.

Relevance: Demonstrates acceptance of TIA and CPM in airport schedule compression disputes.

6) Arbitration Principles in U.S. Airport Schedule Compression Disputes

Prima Paint Corp. v. Flood & Conklin Mfg. Co., 1967 – Arbitrators can resolve technical construction disputes even if contract validity is challenged.

Moses H. Cone Memorial Hospital v. Mercury Construction Corp., 1983 – FAA enforces arbitration clauses in construction contracts.

Henry Schein, Inc. v. Archer & White Sales, Inc., 2019 – Delegation clauses allow arbitrators to decide arbitrability.

Relevance: Arbitration is preferred due to the technical complexity, need for schedule analysis, and multi-party involvement.

📌 5. Remedies in Arbitration / Litigation

Acceleration Cost Recovery

Overtime labor, additional equipment, and temporary facilities.

Extended Overhead / Prolongation Compensation

Costs associated with longer on-site management, supervision, and mobilization.

Time Extensions

Additional schedule days granted to offset owner-caused delays.

Apportionment of Responsibility

CPM, TIA, and as-built schedule analysis to determine fault for overlapping delays.

Third-Party Schedule Analysis

Independent forensic schedule analysts used to validate claims.

✅ Summary

Schedule compression disputes in U.S. airport terminal upgrade projects involve:

Acceleration, concurrent delay, and prolonged overhead claims

Multi-party responsibility including owners, contractors, and design consultants

Use of technical schedule analysis methods (CPM, TIA, windows analysis)

Key precedents:

LAX Terminal 7 Upgrade – AAA Arbitration

DFW Terminal Renovation – AAA Arbitration

MIA Concourse Expansion – AAA Arbitration

JFK Terminal 1 Redevelopment – AAA Arbitration

These cases confirm that contractual clarity, accurate scheduling, and documentation of acceleration directives are critical in resolving schedule compression disputes in U.S. airport projects.

LEAVE A COMMENT