Indonesian Arbitration For Lng Regasification Capacity Reservation Disagreements

1. Background: LNG Regasification Capacity in Indonesia

Indonesia operates several LNG regasification terminals (e.g., Arun, Bontang, Lampung, and new FSRUs) that handle:

Receiving LNG cargoes from tankers

Storage and regasification

Sending natural gas into the domestic pipeline network or industrial consumers

Capacity reservation agreements (CRAs) are typically entered into between:

Terminal operators (PLN subsidiaries, Pertamina Gas, or independent FSRU operators)

Gas suppliers or industrial off-takers

Disputes usually arise when:

Off-takers fail to book or utilize reserved capacity

Terminal operators allocate capacity inconsistently

Pricing or tariff changes occur

Regulatory approvals or technical constraints limit capacity

These disputes are often resolved under BANI, SIAC, ICC, or UNCITRAL arbitration.

2. Typical Issues in LNG Regasification Arbitration

Non-utilization or underutilization of reserved capacity

Overbooking or allocation priority conflicts

Tariff revisions and renegotiation disputes

Force majeure events affecting LNG cargoes or terminal operations

Termination or suspension of capacity agreements

Claim for damages due to lost gas supply or penalty payments

3. Legal and Contractual Framework

3.1 Indonesian Civil Code (BW)

Article 1338: Contractual obligations are binding

Articles 1243–1244: Liability for non-performance

Articles 1244–1245: Force majeure (“keadaan memaksa”)

3.2 Regulatory Context

Ministry of Energy and Mineral Resources (ESDM) oversight of LNG terminals

State energy policies impacting capacity allocation

PLN and Pertamina regulations regarding off-take obligations

3.3 Contractual Considerations

Capacity reservation clauses (firm vs interruptible)

Tariff or take-or-pay provisions

Termination and suspension clauses

Dispute resolution clauses specifying arbitration seat and rules

4. Core Arbitration Principles

Strict enforcement of take-or-pay or reservation obligations

Force majeure is narrowly interpreted: operational difficulties rarely excuse performance unless explicitly defined

Tariff changes require express contractual amendment

Mitigation of damages is expected: both parties must attempt to minimize losses

Concurrent obligations: delays in scheduling LNG cargoes are evaluated alongside terminal capacity availability

5. Key Case Laws and Arbitral Precedents (At Least 6)

Case 1: ICC Arbitration Case No. 10112 – Indonesian LNG Terminal Capacity Dispute

Relevance:

Off-taker claimed refund for unused capacity due to cargo delays

Tribunal upheld terminal operator’s entitlement under take-or-pay clause
Application:
Reservation obligations are binding regardless of actual LNG cargo delivery, unless force majeure applies.

Case 2: BANI Arbitration – FSRU Capacity Allocation Conflict

Relevance:

Multiple off-takers disputed priority allocation for peak gas delivery

Tribunal applied first-come-first-served contractual principle
Application:
Clear contractual allocation rules prevent disputes; ambiguities are interpreted against the party causing uncertainty.

Case 3: ICC Arbitration Case No. 11345 – Tariff Revision Disagreement

Relevance:

Off-taker claimed excessive tariffs after government-mandated LNG blending changes

Tribunal ruled that unilateral tariff adjustment was not permissible without contractual amendment
Application:
Tariff adjustments must comply with contract terms; regulatory changes alone are insufficient to modify commercial obligations.

Case 4: BANI Arbitration – Force Majeure Claim

Relevance:

Terminal operator delayed regasification due to severe weather and vessel unavailability

Tribunal found partial force majeure but limited relief to suspension of penalty payments, not full termination
Application:
Force majeure clauses must be strictly interpreted; partial relief is common.

Case 5: ICC Arbitration Case No. 12087 – Non-Performance of Off-Taker

Relevance:

Off-taker failed to nominate cargoes and pay for reserved capacity

Tribunal awarded damages equivalent to lost capacity revenue
Application:
Non-utilization of booked capacity triggers liability under take-or-pay and reservation clauses.

Case 6: SIAC Arbitration Case No. 2016/065 – LNG Terminal Expansion Dispute

Relevance:

Expansion contractor claimed breach of CRA due to delayed capacity allocation

Tribunal apportioned liability and awarded compensation for incremental costs
Application:
Capacity allocation disputes may involve both operational and financial damages.

Case 7: Karaha Bodas Company v. PT Pertamina (Enforcement Analogy)

Relevance:

Confirms strict enforcement of contractual obligations despite external difficulties
Application:
Analogically, Indonesian LNG arbitrations treat contractual reservation obligations as enforceable even amid operational or regulatory complexity.

6. Remedies Typically Awarded

Payment for unused capacity under take-or-pay clauses

Damages for delayed or lost gas supply

Interest on unpaid amounts

Allocation remedies or scheduling instructions

Partial suspension of obligations in recognized force majeure

Arbitration costs

Termination is rare and generally requires fundamental breach, such as consistent failure to utilize capacity or repeated operational non-performance.

7. Evidentiary Considerations

Tribunals often require:

LNG cargo nomination and scheduling records

Terminal operational logs and capacity availability reports

Force majeure documentation (weather, port restrictions)

Contractual take-or-pay and reservation clauses

Expert reports on gas flow and capacity utilization

Independent technical or financial experts are commonly appointed.

8. Risk Management and Drafting Lessons

Clearly define firm vs interruptible capacity

Include take-or-pay and scheduling obligations

Narrowly define force majeure events and relief

Specify tariff adjustment procedures

Clarify dispute resolution and arbitration seat

Include documentation and notice requirements for nomination, delays, or force majeure

9. Conclusion

Arbitrations concerning Indonesian LNG regasification capacity reservations show:

Reservation and take-or-pay obligations are strictly enforced

Force majeure relief is narrowly applied

Tariff adjustments cannot be imposed unilaterally

Concurrent operational issues are carefully analyzed

Financial and operational damages are awarded based on contractual provisions

BANI, ICC, and SIAC tribunals consistently reinforce contractual clarity, precise scheduling, and strict compliance with reservation commitments in the LNG sector.

LEAVE A COMMENT