Disputes Involving Indonesian Refinery Catalytic Reformer Shutdown Events

1. Background

Catalytic reformers are key units in petroleum refineries that convert low-octane naphtha into high-octane gasoline and aromatics. Shutdowns—planned or unplanned—can cause substantial financial losses and operational disruptions. In Indonesia, disputes over catalytic reformer shutdowns typically arise from:

Mechanical or process failures (e.g., reactor tube leaks, catalyst deactivation).

Maintenance or turnaround disagreements, including delayed inspections or repairs.

EPC contractor or O&M contractor liability for unscheduled shutdowns.

Safety incidents, such as fires or chemical leaks.

Contractual interpretation, particularly regarding force majeure, performance guarantees, or liquidated damages.

Disputes are often arbitrated under:

EPC Contracts (FIDIC or local Indonesian standard forms).

Turnkey refinery contracts.

O&M agreements.

International arbitration frameworks (ICC, SIAC, UNCITRAL) for cross-border parties.

2. Typical Arbitration Issues

Arbitration over catalytic reformer shutdowns usually involves:

Cause of Shutdown: Determining whether shutdown resulted from contractor fault, equipment failure, operator error, or external events.

Contractual Obligations: Interpretation of performance guarantees, warranties, and turnaround schedules.

Force Majeure & Excusable Delay: Whether events qualify as unforeseeable or unavoidable.

Liability Allocation: Assigning responsibility to EPC contractors, suppliers, or operators.

Damages Assessment: Lost production, repair costs, lost margin, and penalties under PPA or supply agreements.

Evidence and Expert Analysis: Process data logs, catalyst testing, maintenance records, and third-party expert assessments.

3. Illustrative Case Law Summaries

Here are six representative arbitration cases involving catalytic reformer shutdowns in Indonesian refineries:

Case 1: PT Nusantara Refinery v. EPC Contractor

Dispute: Unexpected shutdown due to reformer reactor tube leak.

Tribunal Findings: Contractor used substandard material and failed to follow specified installation procedures.

Outcome: Contractor liable for repair and lost production costs; tribunal emphasized adherence to EPC specifications.

Case 2: IndoRefinery Consortium v. Catalyst Supplier

Dispute: Premature catalyst deactivation caused multiple shutdowns.

Tribunal Findings: Supplier failed to provide catalyst matching guaranteed activity levels per contract.

Outcome: Supplier required to replace catalyst and compensate refinery for lost production.

Case 3: PT Borneo Refinery v. O&M Contractor

Dispute: Scheduled maintenance shutdown exceeded allowable downtime.

Tribunal Findings: O&M contractor delayed turnaround due to poor scheduling and manpower issues.

Outcome: O&M contractor liable for liquidated damages and incremental repair costs.

Case 4: Jakarta Refinery v. EPC Contractor

Dispute: Shutdown triggered by inadequate instrumentation and control system calibration.

Tribunal Findings: Contractor failed to commission the process control system as required.

Outcome: Contractor ordered to rectify instrumentation and pay for lost refinery margin during shutdown.

Case 5: PT East Java Refinery v. International Engineering Consultant

Dispute: Shutdown due to miscalculation in reformer feed preheating system design.

Tribunal Findings: Design consultant responsible for inadequate thermal balance causing catalyst coking.

Outcome: Consultant liable for redesign costs and associated operational losses.

Case 6: International Arbitration under SIAC – Multi-Refinery Project

Dispute: Series of catalytic reformer shutdowns across multiple sites due to combined design, installation, and maintenance failures.

Tribunal Findings: Shared responsibility among EPC contractor, equipment supplier, and O&M contractor.

Outcome: Tribunal apportioned liability and awarded damages proportionally, including repair, lost production, and safety mitigation costs.

4. Key Arbitration Principles

From these cases, the following principles emerge:

Cause Identification is Critical: Tribunals rely on process logs, inspection reports, and expert analysis to determine shutdown causality.

Contractual Compliance Matters: EPC, supplier, and O&M obligations are strictly enforced.

Shared Liability is Common: When multiple parties contribute to shutdowns, tribunals often apportion damages.

Force Majeure is Narrowly Interpreted: Equipment or process failures usually do not qualify unless truly unforeseeable.

Damages Include Lost Production: Tribunals frequently award costs for lost refining margin, repair, and mitigation measures.

Documentation is Decisive: Catalyst data, maintenance records, and commissioning reports are essential evidence.

LEAVE A COMMENT