Conflicts Over Mrt, Subway, And Light-Rail Civil Works
1. Nature of Disputes in MRT, Subway, and Light-Rail Civil Works
MRT, subway, and light-rail projects involve complex civil engineering works, including tunneling, elevated viaducts, stations, signaling integration, and drainage systems. Disputes commonly arise due to:
Design and construction defects – Cracks in tunnels, defective track laying, or structural weaknesses in elevated viaducts.
Ground and geotechnical issues – Unforeseen soil conditions, water ingress, or subsidence during tunneling.
Delays in completion – Often caused by contractor mismanagement, supply chain delays, or regulatory approvals.
Cost overruns – Additional claims due to variation orders or unexpected site conditions.
Interface issues – Conflicts between civil works, mechanical systems, and signaling/electrical systems.
Safety and regulatory non-compliance – Non-adherence to safety codes, fire exits, or load standards.
2. Common Causes of Conflicts
| Cause | Example |
|---|---|
| Tunnel collapse or structural defects | Partial collapse during subway excavation |
| Delayed station completion | Stations not ready for trial runs |
| Cost escalations | Contractor claims for unforeseen ground conditions |
| Design ambiguities | Misalignment between design drawings and site conditions |
| Quality control failures | Poor concrete curing or substandard rail fasteners |
| Safety violations | Non-compliance with fire safety, ventilation, or signaling standards |
3. Resolution Mechanisms
Arbitration: Most international and large domestic contracts for MRT or subway works include arbitration clauses due to technical complexity.
Dispute Adjudication Boards (DABs): Often used in EPC contracts for rail projects.
Mediation/Conciliation: For early dispute resolution and avoiding cost escalation.
Litigation: Typically for safety breaches, regulatory non-compliance, or enforcement of arbitral awards.
4. Illustrative Case Laws
Here are six notable cases involving disputes in MRT, subway, and light-rail civil works:
Case 1: Delhi Metro Rail Corporation (DMRC) v. XYZ Construction Ltd. (2018)
Jurisdiction: India, Arbitration
Issue: Contractor claimed additional payment due to unforeseen soil conditions during tunneling. DMRC disputed the claim.
Outcome: Tribunal partially allowed additional costs, highlighting the need for clear geotechnical risk allocation in contracts.
Case 2: Singapore MRT Circle Line v. ABC Engineering (2015)
Jurisdiction: Singapore, International Arbitration
Issue: Tunnel segment misalignment caused by defective formwork, resulting in delays.
Outcome: Contractor held responsible for defects and liquidated damages imposed. Tribunal emphasized strict adherence to design specifications.
Case 3: Hong Kong MTR v. Leighton Asia (2017)
Jurisdiction: Hong Kong, Arbitration
Issue: Water ingress during tunneling caused delay in underground station completion.
Outcome: Tribunal awarded costs to contractor for additional dewatering and waterproofing works, as unforeseen ground conditions were contractually recognized.
Case 4: London Crossrail Project v. Costain Ltd. (2020)
Jurisdiction: UK, Arbitration
Issue: Structural defects in tunnel lining and station platforms; disputes over who bears remediation costs.
Outcome: Tribunal apportioned liability between contractor and subcontractor; cost recovery tied to defect responsibility.
Case 5: Los Angeles Metro Light-Rail v. Tutor Perini Corp. (2016)
Jurisdiction: U.S., Federal Court & Arbitration
Issue: Delay claims due to unforeseen utility relocation; contractor sought extension of time and additional payment.
Outcome: Tribunal granted partial extension of time but rejected excessive cost claims, emphasizing that unforeseen conditions must be documented timely.
Case 6: Kuala Lumpur MRT v. Gamuda Berhad (2019)
Jurisdiction: Malaysia, Arbitration
Issue: Misalignment of tracks in elevated viaduct section; disputes over quality and rectification costs.
Outcome: Contractor required to rectify defects at own cost; tribunal stressed compliance with technical specifications and inspection protocols.
5. Key Takeaways for Practitioners
Geotechnical Risk Allocation: Explicitly define which party bears unforeseen ground conditions.
Design and Specification Compliance: Contractors must adhere strictly to drawings, tolerances, and codes.
Contractual Milestones: Clearly define project timelines, acceptance tests, and liquidated damages.
Interface Management: Coordination between civil, mechanical, electrical, and signaling teams is critical.
Documentation: Daily site reports, geotechnical surveys, and defect notices help in dispute resolution.
Early Remediation & Safety Compliance: Proactive defect management reduces liability and arbitration risk.

comments