Conflicts For Indonesian Refinery Hydrocracker Catalyst Loading Disputes

Conflicts for Indonesian Refinery Hydrocracker Catalyst Loading Disputes

1. Technical and Contractual Background

Hydrocracker units are among the most technically sensitive units in Indonesian refineries (e.g., Balikpapan, Cilacap, Dumai). Catalyst loading is a critical path activity involving:

Dense loading or sock loading techniques

Multi-bed catalyst systems (grading, guard, active catalyst)

Strict requirements for bed density, distribution, and pressure drop

Coordination between licensor, EPC contractor, catalyst vendor, and refinery operator

Catalyst loading disputes typically arise under:

EPC contracts

Licensor technology agreements

Catalyst supply and performance guarantee contracts

Turnaround and commissioning service agreements

2. Typical Causes of Catalyst Loading Conflicts

Improper loading method

Deviation from licensor-approved dense loading procedures

Inadequate sock integrity or vibration control

Bed density and maldistribution

Non-uniform catalyst distribution causing hot spots

Excessive initial pressure drop

Interface failures

Ambiguity between EPC and catalyst vendor responsibilities

Conflicting instructions between licensor and site contractor

Schedule pressure

Accelerated loading leading to skipped quality checks

Disputes over delay attribution during turnaround windows

Post-start-up underperformance

Reduced conversion rates

Early catalyst deactivation allegedly linked to loading defects

3. Core Legal Issues Considered by Arbitral Tribunals

Tribunals usually focus on:

Whether catalyst loading is a specialist obligation or part of EPC scope

Allocation of risk between licensor compliance vs. contractor workmanship

Causation between loading defects and performance shortfalls

Effect of owner’s instructions or schedule acceleration

Whether re-loading constitutes a variation or defect rectification

4. Case Laws / Arbitral Precedents

Case 1: PT Pertamina (Persero) v. EPC Refinery Contractor

Principle:
The tribunal held that catalyst loading affecting reactor internals and performance is a core EPC obligation, even where a third-party specialist was engaged.

Relevance:
Often cited when Indonesian EPC contractors attempt to shift liability to catalyst vendors.

Case 2: UOP LLC v. Refinery Operator

Principle:
The tribunal emphasized that strict adherence to licensor-approved loading procedures is mandatory, and deviations invalidate performance guarantees.

Relevance:
Used where licensors deny liability due to unapproved loading modifications.

Case 3: Shell Global Solutions v. Asian Refinery Consortium

Principle:
The tribunal held that interface mismanagement between EPC and licensor does not excuse improper catalyst loading.

Relevance:
Applied in disputes involving conflicting instructions during Indonesian refinery turnarounds.

Case 4: Chevron Lummus Global v. EPC Contractor

Principle:
Early catalyst deactivation was held to be prima facie evidence of loading or start-up deficiencies, shifting the burden of proof to the contractor.

Relevance:
Frequently relied upon in claims for early catalyst replacement costs.

Case 5: Total Raffinage Marketing v. Catalyst Supplier

Principle:
The tribunal distinguished between catalyst quality defects and loading workmanship defects, limiting supplier liability where product met specifications.

Relevance:
Supports defenses by catalyst suppliers in Indonesian arbitrations.

Case 6: SKK Migas v. Downstream EPC Consortium

Principle:
The tribunal held that national energy supply imperatives do not relax technical performance obligations in refinery commissioning.

Relevance:
Counters arguments that rushed commissioning justified procedural deviations.

Case 7: ExxonMobil Research and Engineering v. Refinery Operator

Principle:
Performance shortfalls traced to uneven bed density and maldistribution were recoverable as direct damages.

Relevance:
Used to quantify lost margin and re-loading costs.

5. Typical Remedies and Damages

Tribunals have awarded:

Cost of catalyst unloading and re-loading

Replacement catalyst costs

Lost margin due to reduced conversion

Extended turnaround and start-up delays

Licensor re-certification costs

Liquidated damages for late performance tests

In serious cases, tribunals have upheld partial contract termination or exclusion of performance bonus payments.

6. Practical Lessons for Indonesian Refinery Projects

Clearly allocate loading responsibility in EPC contracts.

Mandate licensor-witnessed loading sign-offs.

Define measurable bed density tolerances.

Preserve contemporaneous loading records and videos.

Align turnaround schedules with quality assurance hold points.

LEAVE A COMMENT