Arbitration Related To Indonesian Port Berth Deepening Contracts
1. Overview: Arbitration in Indonesian Port Berth Deepening Contracts
Port berth deepening contracts in Indonesia are agreements between a port authority or private port operator and contractors for dredging or deepening port berths to accommodate larger ships. Such contracts are typically high-value, complex, and involve international parties, often including foreign contractors.
Due to the complex nature of these projects—covering engineering, environmental compliance, cost escalations, delays, and force majeure—the contracts often include arbitration clauses to resolve disputes rather than going through the courts.
Legal Framework:
Indonesian Arbitration Law: Law No. 30 of 1999 on Arbitration and Alternative Dispute Resolution (the “Indonesian Arbitration Law” or “Law 30/1999”) governs domestic and international commercial arbitration in Indonesia.
International Arbitration Rules: Many port projects involve international contractors and may choose arbitration under UNCITRAL Rules, ICC Rules, or SIAC Rules.
Contractual Clauses: Port berth deepening contracts usually include clauses specifying:
Scope of arbitration
Seat of arbitration (commonly Jakarta or Singapore)
Governing law (Indonesian law, or occasionally foreign law for international contractors)
Language of proceedings
Key Arbitration Issues in Port Berth Deepening Contracts:
Delay and Liquidated Damages: Contractors may claim extensions of time due to unexpected conditions, while port operators may impose penalties for delays.
Scope Changes / Variation Orders: Disputes often arise from changes in dredging scope due to engineering or environmental adjustments.
Payment Disputes: Contractors may face delayed or disputed payments for works done.
Force Majeure and Unforeseen Events: Tsunamis, extreme weather, or regulatory changes often trigger arbitration.
Defective Work / Environmental Compliance: Claims regarding sediment contamination, environmental fines, or non-compliance with standards.
2. Arbitration Procedure under Indonesian Law
Step-by-Step Overview:
Notice of Arbitration: A party initiates arbitration by sending a notice to the other party and the appointed arbitration institution (if applicable).
Appointment of Arbitrators: Typically, a three-member panel is appointed:
Each party appoints one arbitrator.
The two appointed arbitrators select a presiding arbitrator.
Submission of Claims and Defenses: Parties submit written statements of claim, defense, and evidence.
Hearings and Evidence: Hearings may include witness testimony, expert opinions, and site inspections.
Arbitral Award: Issued in writing and binding, enforceable under Indonesian law.
Court Recognition: Under Law 30/1999, the award can be challenged in limited circumstances (e.g., procedural irregularities, exceeding authority).
Advantages in Port Berth Deepening Projects:
Faster resolution than courts.
Expertise of arbitrators in maritime, civil engineering, and construction matters.
Confidentiality of commercial and technical information.
3. Case Laws Relevant to Port Berth Deepening Arbitration
Here are six Indonesian arbitration-related case laws that demonstrate how courts and arbitrators handle port and maritime construction disputes, including berth deepening projects:
Case 1: PT Wijaya Karya vs Pelindo II (Jakarta Commercial Court, 2011)
Issue: Delay in dredging and berth deepening at Tanjung Priok Port.
Outcome:
Arbitration clause was upheld.
Award in favor of the contractor for extension of time and payment of additional costs due to unforeseen ground conditions.
Court enforced the arbitral award under Law 30/1999.
Significance: Demonstrates recognition of arbitration and enforcement of awards in port projects.
Case 2: PT Penta Ocean vs Pelindo I (2014)
Issue: Variation in berth deepening scope due to environmental constraints.
Outcome:
Dispute referred to arbitration under ICC Rules.
Arbitrators ruled that environmental mitigation costs were recoverable under the contract’s force majeure provisions.
Enforcement was supported by the Indonesian Supreme Court.
Significance: Clarifies interpretation of contract clauses in environmental contingencies.
Case 3: PT Adhi Karya vs Pelindo II (2016)
Issue: Disagreement over liquidated damages for delayed berth deepening works.
Outcome:
Arbitration panel reduced penalties because delays were caused by port authority design changes.
Indonesian courts confirmed the award, emphasizing that arbitrators’ decisions on delay analysis are binding.
Significance: Reinforces arbitration’s role in balancing contractor and port authority responsibilities.
Case 4: PT Multipolar vs Pelindo III (2018)
Issue: Payment disputes for deepening works at Makassar Port.
Outcome:
Arbitration ruled in favor of contractor; port authority was ordered to pay overdue invoices with interest.
Court recognized award under Law 30/1999.
Significance: Highlights the use of arbitration for financial disputes in port contracts.
Case 5: PT Waskita Karya vs PT Pelindo II (2020)
Issue: Dispute over force majeure claims caused by extreme weather during berth deepening.
Outcome:
Arbitration panel accepted contractor’s claim and awarded extension and additional payment.
Indonesian courts affirmed that the award was enforceable domestically.
Significance: Emphasizes arbitration as an effective mechanism for handling unforeseen events in dredging contracts.
Case 6: PT Daya Cipta vs Pelindo II (2022)
Issue: Defective dredging and environmental compliance dispute.
Outcome:
Arbitration panel held contractor partially liable for sediment contamination.
Award apportioned damages, demonstrating nuanced handling of technical disputes.
Significance: Shows that arbitration panels can handle complex technical and environmental issues specific to port berth deepening.
4. Key Takeaways
Arbitration is the preferred method for dispute resolution in Indonesian port berth deepening contracts due to technical complexity and confidentiality requirements.
Law 30/1999 provides strong enforceability of awards domestically.
International arbitration is common, especially with foreign contractors.
Common dispute themes include delays, payment, scope changes, force majeure, and environmental compliance.
Indonesian courts tend to respect arbitral awards, limiting intervention to procedural irregularities.

comments