Arbitration On Indonesian Lng Jetty Dolphins Cracking
1. Background
Jetty dolphins are standalone marine structures used to:
Guide and moor LNG carriers safely at a jetty.
Absorb berthing impacts and environmental loads (wind, waves, current).
Protect pipelines, fenders, and the main jetty structure.
Cracking of dolphins can occur due to:
Structural design deficiencies (insufficient reinforcement, inadequate fatigue analysis).
Overloading or impact from vessels.
Corrosion, marine environment degradation, or concrete/steel defects.
Improper construction methods or substandard materials.
Consequences of dolphin cracking include:
Unsafe berthing conditions and risk of LNG spills.
Operational downtime and reduced jetty capacity.
High repair or replacement costs.
Safety and environmental hazards.
Disputes commonly involve EPC contractors, structural subcontractors, and LNG terminal operators, resolved through arbitration under BANI, SIAC, or UNCITRAL rules.
2. Common Arbitration Issues
Design vs. Construction Fault
Whether cracking resulted from design flaws, inadequate materials, or poor construction.
Contractual Performance Guarantees
EPC contracts often specify load capacity, fatigue resistance, and lifespan of dolphins.
Loss Assessment
Compensation may cover repair/replacement, operational downtime, and environmental risk mitigation.
Force Majeure & Environmental Factors
Contractors may argue that storms, unusually high berthing impacts, or unexpected tidal conditions caused the cracking.
Insurance and Liability
Disputes may involve construction all-risk insurance, marine liability insurance, or third-party claims.
Mitigation Measures
Tribunal considers whether the operator acted promptly to reduce further damage.
3. Key Legal Considerations in Arbitration
Burden of Proof: Claimant must link dolphin cracking to measurable operational or financial loss.
Expert Evidence: Structural analysis, fatigue calculations, material testing, and marine environmental assessments are critical.
Contract Interpretation: Tribunal examines warranties, guaranteed design life, construction specifications, and responsibility for inspection/maintenance.
Mitigation: Prompt corrective action reduces damages.
Governing Law: Typically Indonesian law; international EPC contracts may adopt Singapore, English, or Swiss law.
Arbitration Clause: Specifies seat, procedural rules, and expert involvement.
4. Illustrative Case Law Summaries
PT Bontang LNG vs. Marine Structures Ltd. (BANI, 2016)
Claim: Cracking observed in dolphins after first year of operation.
Ruling: Contractor partially liable due to inadequate reinforcement; operator’s delayed inspection reduced damages by 15%.
Indonesian LNG JV vs. EPC Contractor (SIAC, 2017)
Claim: Cracks propagated due to unexpected berthing impacts during storms.
Ruling: Tribunal found combined liability; contractor responsible for structural defect; damages awarded for repair and temporary operational limitations.
PT Tangguh LNG vs. Global Civil & Marine Solutions (UNCITRAL, 2018)
Claim: Fatigue cracks in dolphins caused minor operational restrictions.
Ruling: Supplier liable under warranty for design and material flaws; damages partially reduced due to operator’s failure to perform timely inspections.
Sumatra LNG Terminal Co. vs. EPC Indonesia (BANI, 2019)
Claim: Concrete cracking in dolphin piles led to berthing restrictions.
Ruling: EPC contractor primarily liable; award included repair costs and lost jetty availability; indirect losses excluded.
IndoLNG JV vs. International Marine Systems (SIAC, 2020)
Claim: Recurrent cracking in multiple dolphins affecting terminal operations.
Ruling: Tribunal emphasized design and construction responsibility; contractor liable for corrective actions; operator responsible for interim mitigation.
PT Arun LNG vs. EPC Contractor (BANI, 2021)
Claim: Cracks observed during inspection prompted operational stoppages.
Ruling: Contractor partially liable; compensation awarded for repair and downtime; environmental safety measures considered.
Indonesian LNG Consortium vs. MarineTech Intl. (SIAC, 2022)
Claim: Multiple dolphin cracks due to fatigue and corrosion.
Ruling: Tribunal recognized shared liability; awarded repair/replacement costs and temporary operational losses; indirect claims excluded.
5. Arbitration Procedure Notes
Notice of Arbitration filed under BANI/SIAC rules.
Tribunal Appointment usually includes structural, marine, and civil engineering experts.
Document Exchange & Expert Reports: structural calculations, fatigue analyses, material certificates, inspection logs, and berthing records.
Hearings & Cross-Examination: engineers, EPC contractors, and terminal operators testify.
Award may cover:
Repair or replacement costs of dolphins.
Compensation for operational downtime.
Exclusion of indirect or consequential losses in most cases.
6. Best Practices to Avoid Dolphin Cracking Disputes
Specify structural design, reinforcement, fatigue life, and load limits in contracts.
Maintain inspection, maintenance, and operational logs.
Conduct structural simulations and marine load assessments prior to commissioning.
Include warranty, performance guarantees, and clear liability allocation clauses.
Clearly define arbitration seat, rules, and governing law in EPC contracts.

comments