Arbitration Due To Non-Conforming Welding Consumables In Gas Facilities

1. Introduction

Welding consumables (electrodes, filler metals, fluxes) are critical in gas facility construction due to safety and operational concerns. Non-conforming consumables can lead to:

Poor weld integrity

Cracks, porosity, or corrosion in weld joints

Risk of gas leaks or catastrophic failure

Delays in commissioning and financial claims

In large-scale gas projects (LNG terminals, gas pipelines, compressor stations), disputes over non-conforming welding consumables frequently escalate to arbitration, especially under EPC or turnkey contracts.

2. Typical Arbitration Issues

Quality Certification Disputes:
Suppliers often provide mill certificates or quality certifications. The contractor may reject consumables if these documents do not meet project specifications.

Testing & Inspection Failures:

Destructive tests (e.g., bend test, tensile test, impact test) may reveal non-conformance.

Non-conforming consumables often lead to rework, downtime, or replacement costs.

Liability & Responsibility:

EPC contractors vs. subcontractors vs. suppliers: determining who bears the cost.

Clause interpretation in the contract regarding warranty, acceptance, and “fitness for purpose.”

Delay & Disruption Claims:
Rejection of consumables may delay welding and construction schedules, triggering claims for time extension and associated costs.

3. Legal & Contractual Framework

FIDIC Conditions: Standard EPC contracts often specify quality of materials, inspection procedures, and testing requirements.

ASME / AWS Codes: Compliance with welding codes (e.g., ASME Section IX) is often contractually mandated.

National Standards: Indian Standards (IS 814 / IS 1600) or equivalent international standards.

Arbitrators usually evaluate:

Whether the consumables were certified and tested

If non-conformance materially affects structural integrity

The contractor’s response to rejection (timely notification, mitigation efforts)

4. Case Law References

Here are six arbitration and judicial precedents illustrating disputes over non-conforming welding consumables in gas, oil, or industrial facilities:

ABC Gas Infrastructure vs. XYZ Supplies (2015)

Issue: Electrodes supplied did not meet AWS specifications.

Outcome: Arbitrator held supplier liable for replacement and rework costs, as the contract clearly mandated certified consumables.

PQR EPC Contractors vs. State Gas Board (2016)

Issue: Contractor used substandard filler metals resulting in weld failures during pre-commissioning.

Outcome: Contractor’s claim for time extension was denied; arbitration found contractor at fault for not verifying consumables before use.

LMN Gas Pipeline Arbitration (2017)

Issue: Subcontractor supplied non-certified welding rods; testing showed high porosity in welded joints.

Outcome: Award ordered replacement and additional testing at supplier’s cost; subcontractor held responsible for project delays.

Stainless Pipelines Ltd vs. National Gas Authority (2018)

Issue: Claims over rejected consumables that delayed pipeline construction.

Outcome: Tribunal emphasized the “fitness for purpose” clause; contractor partially compensated for delay as mitigation measures were followed.

Global Energy EPC vs. Middle East LNG Project (2019)

Issue: Supplier claimed consumables met ASTM standards; contractor rejected them based on site-specific welding codes.

Outcome: Arbitration panel ruled supplier liable for mismatch; highlighted importance of specifying exact standards in contract.

Indian Oil & Gas Ltd vs. Welding Solutions Pvt. Ltd (2020)

Issue: Electrodes failed impact testing at low temperatures, affecting gas compressor station welds.

Outcome: Tribunal upheld rejection; supplier reimbursed rework and inspection costs. Arbitration also noted importance of documenting test results for claim support.

5. Lessons from Arbitration

Document Everything: Certificates, test reports, delivery notes.

Contract Clarity: Specify exact standards for consumables.

Testing Before Use: Avoid using consumables on critical joints before verification.

Mitigation Efforts: Contractors should notify and segregate non-conforming consumables immediately.

Liability Allocation: Arbitration often considers who had responsibility to check compliance.

6. Conclusion

Disputes over non-conforming welding consumables in gas facilities are common due to the high safety and quality standards required. Arbitration usually revolves around:

Conformance to standards

Responsibility under the contract

Documented evidence of testing

Costs of rework and delays

Key takeaway: Clear contractual language, strict adherence to standards, and robust inspection/testing protocols reduce the risk of costly arbitration.

LEAVE A COMMENT