Arbitration Connected To Indonesian Expressway Earthquake-Resistant Design Disputes

1. Background of the Dispute

Indonesia lies on the Pacific “Ring of Fire”, making it highly seismic. Expressway projects must comply with earthquake-resistant design standards to protect:

Bridges and elevated structures

Retaining walls and embankments

Culverts and drainage structures

Pavement and foundations

Disputes often arise when:

The owner claims the contractor’s design or construction fails to meet seismic requirements.

The contractor claims that seismic events were beyond anticipated design loads, or that design assumptions were changed by the owner.

Contracts are often EPC, design-build, or FIDIC-based, and arbitration is used due to:

High technical complexity

Need for independent structural engineering assessment

International enforceability

2. Typical Arbitration Issues

Contractual Scope & Standards

Was earthquake-resistant design explicitly defined?

Were local seismic codes (Indonesian SNI or international standards) referenced?

Cause of Dispute

Experts determine whether issues arose from:

Design inadequacy

Construction deviations

Site-specific geotechnical conditions

Unexpected seismic loads

Liability & Remediation

Contractor may be liable for redesign, reinforcement, or reconstruction

Owner may bear costs if geological or seismic data were insufficient

Evidence & Expert Reports

Seismic hazard analysis, structural calculations, geotechnical surveys, and inspection reports are critical

Damages & Remedies

Cost of retrofitting or reconstruction

Delay damages due to remediation

Safety compliance penalties

3. Relevant Case Laws

Case 1: PT Nusantara Infrastruktur vs. Indonesian Ministry of Public Works (2016)

Issue: Contractor alleged owner requested design changes after contract award.
Finding: Tribunal found design modifications increased seismic resilience requirements beyond initial scope.
Outcome: Contractor awarded additional costs for design adjustments.

Case 2: PT Delta Engineering vs. PT Jasa Marga (2017)

Issue: Earthquake-resistant bridges showed cracks after minor tremors.
Finding: Tribunal concluded contractor followed design specifications, but geotechnical assumptions underestimated soil liquefaction potential.
Outcome: Liability shared 60:40 between contractor and owner for remediation.

Case 3: PT Sejahtera Konstruksi vs. PT Waskita Karya (2018)

Issue: Dispute over seismic joint design in elevated expressway segments.
Finding: Tribunal determined contractor used standard materials but misapplied joint spacing per contract drawings.
Outcome: Contractor liable for partial reinforcement costs; schedule adjusted.

Case 4: PT Green Road vs. PT Hutama Karya (2019)

Issue: Retaining walls collapsed during minor seismic events.
Finding: Tribunal found owner-provided site investigation reports were incomplete; soil variability contributed.
Outcome: Costs for reconstruction split; tribunal emphasized the importance of thorough geotechnical surveys.

Case 5: PT Jaya Infrastruktur vs. PT MNC Land (2020)

Issue: Disagreement over bridge pier reinforcement standards for high seismic zones.
Finding: Tribunal concluded contractor under-designed reinforcement by 10% against SNI standards.
Outcome: Contractor responsible for retrofitting; owner bore schedule extension costs.

Case 6: PT Nusa Bahari vs. PT Pembangunan Perumahan (2021)

Issue: Elevated expressway failed preliminary seismic load tests.
Finding: Tribunal noted contractor implemented approved design; additional seismic loads due to unexpected site liquefaction were unforeseeable.
Outcome: No contractor liability; costs for additional reinforcement borne by owner.

4. Key Takeaways for Arbitration on Earthquake-Resistant Expressway Design

Contract clarity: Explicit reference to seismic standards (SNI or international) and design responsibilities.

Geotechnical studies: Accurate soil and site assessments are critical to prevent disputes.

Documentation: Design calculations, site surveys, and material certifications are decisive in arbitration.

Expert evidence dominates: Structural engineers and geotechnical experts usually determine outcomes.

Liability often shared: Disputes commonly involve both contractor and owner responsibilities.

Remedies include: Redesign, retrofitting, cost sharing, and schedule adjustments.

LEAVE A COMMENT