Force Majeure Clauses Post-Brexit Interpretation

1. Post-Brexit Legal Context

A. Retained EU Law and Contractual Interpretation

After Brexit:

EU law is retained but no longer supreme

UK courts may depart from CJEU jurisprudence

Contractual interpretation remains grounded in English common law principles

Key Principle:

Force majeure remains purely contractual, unaffected in structure but influenced in context and application.

2. Core Issues in Post-Brexit Interpretation

A. Does Brexit Qualify as a Force Majeure Event?

1. Express Inclusion

If clauses include:

“Government action”

“Change in law”

“Trade restrictions”

→ Brexit-related consequences may qualify.

2. General Wording

Generic terms like:

“Events beyond reasonable control”

→ Courts interpret narrowly.

Case Law:

Channel Island Ferries Ltd v Sealink UK Ltd [1988] 1 Lloyd’s Rep 323
Emphasizes strict interpretation of clause wording.

B. Foreseeability and Timing

A critical issue post-Brexit is:

Whether Brexit was foreseeable at contract formation

Legal Impact:

If foreseeable → harder to rely on force majeure

If unforeseeable → stronger claim

Case Law:

Edwinton Commercial Corporation v Tsavliris Russ (The Sea Angel) [2007] EWCA Civ 547
Foreseeability and allocation of risk are central to supervening events.

C. Causation Standards

Brexit must cause the non-performance, not merely make it more difficult.

Case Law:

Classic Maritime Inc v Limbungan Makmur Sdn Bhd [2019] EWCA Civ 1102
Introduced strict “but for” causation—party must prove performance would have occurred absent the event.

D. Economic Hardship vs Legal Impossibility

Brexit often results in:

Increased tariffs

Customs delays

Regulatory burdens

However, economic difficulty alone is insufficient.

Case Law:

Tsakiroglou & Co Ltd v Noblee Thorl GmbH [1962] AC 93
Performance still required if alternative methods exist.

E. Self-Induced Non-Performance

Companies cannot rely on Brexit if:

They failed to prepare for known risks

They did not take alternative steps

Case Law:

The Super Servant Two [1990] 1 Lloyd’s Rep 1
Failure to use available alternatives defeats force majeure claims.

F. Mitigation and Reasonable Endeavours

Post-Brexit, parties must show:

Efforts to adapt supply chains

Alternative sourcing

Compliance with new regulations

Case Law:

Bulman & Dickson v Fenwick & Co [1894] 1 QB 179
Obligation to mitigate impact of disruptive events.

3. Brexit-Specific Scenarios

A. Border Delays and Customs Barriers

Usually not sufficient unless they render performance impossible

May qualify if clause includes “government restrictions”

B. Regulatory Divergence

Changes in standards or certifications

May trigger “change in law” provisions

C. Currency Fluctuations

Generally not force majeure

Considered commercial risk

D. Supply Chain Disruption

Supplier failure alone insufficient unless expressly covered

Case Law:

Seadrill Ghana Operations Ltd v Tullow Ghana Ltd [2018] EWHC 1640 (Comm)
Event must be the effective cause of non-performance.

4. Interaction with Frustration Doctrine

If force majeure clause does not apply:

Parties may argue frustration

However:

Threshold is high

Contract automatically terminates

Case Law:

Davis Contractors Ltd v Fareham UDC [1956] AC 696
Mere hardship or delay is insufficient.

5. Drafting Implications Post-Brexit

A. Express Brexit Clauses

Modern contracts include:

“Brexit” as a defined event

“Change in law or trade regime” provisions

B. Risk Allocation

Corporations must clearly allocate:

Tariff risks

Customs delays

Regulatory compliance costs

C. Hybrid Clauses

Combine force majeure with material adverse change (MAC) clauses

6. Key Case Law Summary

Classic Maritime v Limbungan (2019) – “But for” causation

Seadrill v Tullow (2018) – Effective cause test

Channel Island Ferries v Sealink (1988) – Strict interpretation

The Sea Angel (2007) – Foreseeability and risk allocation

The Super Servant Two (1990) – Self-induced impossibility

Tsakiroglou v Noblee Thorl (1962) – Economic hardship insufficient

Bulman v Fenwick (1894) – Mitigation duty

Davis Contractors v Fareham (1956) – Frustration doctrine

7. Practical Corporate Guidance

To manage post-Brexit risks:

Draft specific force majeure clauses covering:

Trade barriers

Regulatory changes

Border delays

Include detailed notice and mitigation provisions

Use alternative sourcing strategies

Maintain documented evidence of causation and mitigation

8. Conclusion

Post-Brexit interpretation of force majeure clauses reflects continuity in legal principles but change in commercial context. Courts emphasize:

Strict contractual interpretation

Clear causation between Brexit event and non-performance

Allocation of foreseeable risks

Ultimately, Brexit has made force majeure clauses more commercially significant but legally demanding, requiring precise drafting and strong evidentiary support for successful reliance.

LEAVE A COMMENT