Arbitration related to Indonesian coal plant air preheater foulin
1. Introduction: Nature of the Dispute
Air preheater fouling disputes arise frequently in coal-fired thermal power plants because the air preheater is a critical heat-recovery component. In Indonesian coal plants, especially those using high-moisture or high-ash coal, fouling can significantly reduce boiler efficiency.
An air preheater transfers heat from outgoing flue gas to incoming combustion air. Fouling occurs when deposits accumulate on heat-transfer surfaces due to:
- fly ash deposition;
- ammonium bisulfate formation;
- sulphur compounds;
- unburnt carbon;
- excessive coal ash content;
- inadequate soot-blowing design;
- poor combustion tuning.
Typical arbitration disputes involve claims between:
- Owner / Independent Power Producer (IPP)
and - EPC Contractor / Boiler Supplier / OEM
regarding:
- failure to achieve guaranteed heat rate;
- excessive auxiliary power consumption;
- forced outages;
- inability to maintain boiler efficiency;
- increased coal consumption;
- cleaning and modification costs;
- liquidated damages.
Indonesian coal supply and power-project disputes often involve complex contractual relationships between coal suppliers, EPC contractors and plant operators. Arbitration clauses are frequently used for resolving such commercial disputes.
2. Typical Arbitration Scenario: Indonesian Coal Plant Air Preheater Fouling
Facts Pattern
A 600 MW Indonesian coal-fired power plant is commissioned under an EPC contract.
The EPC contractor guarantees:
- boiler efficiency: 88%;
- guaranteed heat rate;
- availability: 85–90%;
- continuous operation for a specified period.
After commissioning:
- air preheater differential pressure increases rapidly;
- gas-side pressure loss exceeds design values;
- boiler efficiency decreases;
- fans operate at higher load;
- plant consumes additional coal.
The owner alleges:
"The air preheater design was defective and incapable of handling Indonesian coal characteristics."
The EPC contractor argues:
"The coal supplied by the owner had excessive ash, moisture and sulphur beyond design parameters."
The arbitration tribunal must determine:
- Was the equipment defectively designed?
- Was coal quality outside contractual assumptions?
- Was operation and maintenance inadequate?
- Are damages recoverable?
- Who bears performance risk?
3. Main Legal Issues in Arbitration
A. Contractual Performance Guarantees
Most EPC contracts contain:
- guaranteed performance clauses;
- boiler efficiency guarantees;
- heat-rate guarantees;
- emission guarantees;
- reliability guarantees.
The owner argues that air-preheater fouling violates these guarantees.
The contractor usually relies on:
- design coal specifications;
- operating conditions;
- exclusions;
- maintenance obligations.
The tribunal examines whether the guarantee was:
- absolute;
- conditional;
- dependent on fuel quality.
B. Defect vs Operating Condition
The central technical question:
Was fouling caused by:
Contractor Responsibility
Examples:
- incorrect heat-transfer surface design;
- inadequate corrosion allowance;
- wrong material selection;
- insufficient soot blower capacity;
- poor CFD modelling.
OR
Owner Responsibility
Examples:
- excessive ash coal;
- improper combustion;
- poor cleaning;
- operation outside design envelope.
C. Delay and Loss Claims
Owners commonly claim:
Direct damages:
- additional coal cost;
- repair expenses;
- replacement of baskets;
- shutdown losses.
Consequential damages:
- lost electricity sales;
- capacity payments;
- contractual penalties.
Contractors usually rely on:
- limitation clauses;
- exclusion of consequential damages;
- liquidated damages caps.
4. Applicable Indonesian Arbitration Principles
Indonesian arbitration is primarily governed by:
- Law No. 30 of 1999 concerning Arbitration and Alternative Dispute Resolution.
Common arbitration issues include:
- tribunal jurisdiction;
- expert evidence;
- technical causation;
- contractual interpretation;
- enforcement of awards.
For international energy projects, parties may also select:
- ICC Arbitration;
- SIAC Arbitration;
- UNCITRAL Arbitration.
5. Technical Evidence Before the Tribunal
Air-preheater arbitration normally requires:
(A) Engineering Evidence
Experts analyse:
- fouling rate;
- pressure-drop trends;
- flue gas temperature;
- ash chemistry;
- deposit composition.
(B) Coal Analysis
Important parameters:
- ash percentage;
- sulphur content;
- moisture;
- volatile matter;
- calorific value.
(C) Performance Testing
Tribunals consider:
- ASME PTC standards;
- OEM guarantees;
- commissioning tests;
- operational logs.
6. Relevant Case Laws
Case Law 1: Fiona Trust & Holding Corporation v Privalov (2007)
Principle:
Arbitration clauses should be interpreted broadly.
Relevance:
In an Indonesian coal plant dispute, the contractor may argue that the arbitration clause only covers contractual payment disputes.
The owner may argue that:
- design defects;
- performance failure;
- warranty claims
are also covered.
The tribunal applies the Fiona Trust principle that commercial parties generally intend all disputes arising from their relationship to fall within arbitration.
Application:
Air-preheater fouling claims arising from EPC performance obligations would normally fall within arbitration jurisdiction.
Case Law 2: Mitsubishi Motors Corp v Soler Chrysler-Plymouth Inc. (1985)
Principle:
Commercial disputes involving technical and contractual obligations are arbitrable.
Relevance:
A coal plant performance dispute involves:
- engineering guarantees;
- economic losses;
- contractual obligations.
The case supports arbitration of complex industrial disputes.
Application:
Claims regarding boiler efficiency and air-preheater reliability can be resolved through arbitration rather than court litigation.
Case Law 3: Hadley v Baxendale (1854)
Principle:
Damages are recoverable only if they arise naturally from the breach or were within the parties' contemplation.
Relevance:
The owner may claim:
- lost generation revenue;
- additional fuel expenses;
- business interruption.
The contractor may argue these are remote losses.
Tribunal Analysis:
The tribunal asks:
Was loss of generation:
- foreseeable?
- contemplated under the EPC contract?
Application:
Additional coal consumption caused by fouling may be recoverable, but speculative future losses may be rejected.
Case Law 4: MT Højgaard A/S v E.ON Climate & Renewables UK Robin Rigg East Ltd (2017)
Principle:
A contractor may remain liable where it provides a performance obligation even if it complied with industry standards.
Relevance:
This is highly relevant to EPC disputes.
The contractor may argue:
"The air-preheater design complied with accepted engineering practice."
The owner responds:
"The contract required guaranteed performance, not merely reasonable workmanship."
Tribunal Approach:
Where the contract contains absolute performance guarantees, compliance with industry practice may not eliminate liability.
Case Law 5: ICC Case No. 11210 (Construction Arbitration)
Principle:
Technical performance guarantees in construction contracts must be interpreted according to contractual risk allocation.
Relevance:
In power plant arbitration, tribunals frequently examine:
- guaranteed output;
- efficiency requirements;
- testing procedures.
Application:
If the EPC contract allocated coal compatibility risk to the contractor, fouling liability may follow.
If coal quality risk remained with the owner, liability may be reduced.
Case Law 6: Transfield Shipping Inc v Mercator Shipping Inc (The Achilleas) (2008)
Principle:
Contract damages depend upon whether the loss falls within the assumed responsibility of the breaching party.
Relevance:
A coal plant owner may claim:
- electricity-market losses;
- replacement power costs;
- revenue losses.
The contractor may argue these were outside the contractual risk assumed.
Application:
The tribunal separates:
Recoverable:
- repair costs;
- efficiency losses;
- additional fuel consumption.
Possibly excluded:
- speculative market losses.
7. Possible Arbitration Arguments
Owner's Arguments
1. Defective Design
The EPC contractor:
- underestimated Indonesian coal characteristics;
- failed to design adequate cleaning systems;
- selected unsuitable materials.
2. Failure of Guarantee
The contractor promised:
- efficiency;
- reliability;
- availability.
Actual operation failed.
3. Breach of Fitness Obligation
The plant was not suitable for intended operation.
Contractor's Arguments
1. Coal Quality Defence
The contractor argues:
Indonesian coal supplied contained:
- higher ash;
- higher moisture;
- higher sulphur.
Therefore fouling was unavoidable.
2. Operation and Maintenance Failure
Possible causes:
- insufficient soot blowing;
- poor combustion adjustment;
- delayed cleaning.
3. Exclusion Clauses
The EPC contract may exclude:
- fuel-related problems;
- abnormal operation;
- owner-controlled conditions.
8. Tribunal's Likely Determination
A tribunal would normally apply a causation test:
Step 1:
Was the coal within contractual specifications?
If yes → contractor risk increases.
If no → owner risk increases.
Step 2:
Was fouling predictable?
Modern coal plant designers must anticipate:
- ash characteristics;
- sulphur behaviour;
- deposit formation.
Step 3:
Did the contractor provide warnings?
Failure to warn may create liability.
Step 4:
Was mitigation attempted?
Failure by either party to mitigate damages affects compensation.
9. Possible Remedies
The arbitral tribunal may order:
Contractor Liability
- replacement of air-preheater baskets;
- redesign;
- modification costs;
- liquidated damages;
- efficiency compensation.
Shared Liability
Where both parties contributed:
Example:
- contractor underestimated coal variability;
- owner supplied unsuitable coal.
Tribunal may apportion damages.
Owner Liability
Where:
- coal exceeded specifications;
- maintenance was inadequate;
- operation was improper.
10. Conclusion
Indonesian coal plant air-preheater fouling arbitration is fundamentally a technical causation and contractual risk-allocation dispute.
The decisive issues are:
- contractual coal specifications;
- EPC performance guarantees;
- engineering design responsibility;
- operational practices;
- foreseeability of damages.
Modern arbitration tribunals generally follow the principles established in cases such as Fiona Trust, Mitsubishi, Hadley v Baxendale, MT Højgaard, ICC construction arbitration jurisprudence, and The Achilleas to determine whether fouling represents:
- defective engineering,
- abnormal operating conditions,
- fuel-quality problems,
- or shared responsibility.

comments